M25 Junction 27 Bank Remediation

Project :

Full remediation works to bank landslide located at Junction 27 on the M25.

Description :

Luxus Buan was appointed by KSC Barton Limited, a groundworks contractor, to provide a Project Management service for a complicated bank stabilisation scheme on the M25. The entire bank was removed in two stages 7 meters down with Class 1A (Highways specification) material to be re-compacted in appropriate layers complete with installation of new land drain. It was a fast-track project with an 8 week duration completed on time and budget to the client’s satisfaction. The bank is located between two slip roads making vehicle access and logistics challenging and required certain operations to be carried out at night.